Client: Water Board Scheldestromen / Project Bureau Zeeweringen
Contractor: Heijmans
Dimensions: 32.400 m2
Duration: 2015

Dyke reinforcement Zuidhoek Zierikzee is one of the dyke works awarded by Rijkswaterstaat for the protection of primary dykes in the county of Zeeland.

The area extends from the eastern port channel of Zierikzee, under the Zeeland Bridge through to Haven de Val. The dyke route is 2.5 kilometers long.

Scheldestromen Water is after completion of the work responsible for the management of the dyke.

The dykes are reinforced by installing concrete pillars on the slopes. The concrete pillars of Martens were chosen for this embankment work. These "Hillblocks" are KOMO-certified and comply with the requirements of the "Zetsteen van beton 7024" standard.

One of the EMVI (Economically Most Advantageous Tender) criteria in the tender contract was delivering concrete pillars which are more substainably produced than conventional concrete pillars. The determining herein was to reduce the amount of concrete in the entire work as much as possible.
The Hillblocks are ideal for this. For Hillblocks is in fact 30% less concrete needed. This can not only achieve a substantially higher fictional discount, but there is also considerably less transport required. This is less damaging to the environment and also nuisance for traffic and environment will be minimized.
.


Back to projects



NL EN


CALCULATIONTOOL WAVE REDUCTION Read more
Model Testing Report DMC 1:10 Read more
Document Deltares regarding the calculation of the roughness factor of Hillblocks. Read more
VIDEOS Hillblock Read more


General information
Disclaimer
Privacy statement
Sitemap
Links  
Colofon   


Follow us

Facebook  Twitter  LinkedIn  Google+